Modernization of the 110/20 kV BLEJEȘTI transformer station
The work consisted of the replacement of the 110 kV, 20 kV primary and secondary circuit equipment, with the reuse of the existing supports. The command-control system of the entire station was changed, creating a highly efficient SCADA telecontrol system. The complexity of the work consisted in the difficulty of organizing the execution, considering that the station was operating throughout the duration of the works. Also, for the reuse of the existing concrete supports in the station, respectively the rulers, they were repaired with carbon fiber and a series of special resins and cements due to their high degree of degradation.