For SEN, this line represents an important artery for transporting electricity produced by CNE Cernavodă as well as by the wind power plants in Dobrogea.
As part of the project, rehabilitation works were carried out to increase the degree of operational safety.
The expertise and experience of our teams has been proven once again. The following were achieved within the project:
- Works on the foundations of the LEA pillars
- Work on earthing sockets
- Works to be performed on active conductors
- Works on protective conductors
- Day beaconing of LEA
- Work performed on insulator chains and protective conductor connections
- Regulation of the LEA route with overcrossed objectives
- Access roads