Modernization of the 220/110/20 kV Vetiș Station
The modernization of the 220/110/20 kV Vetiș Station - represents an important contract from the company's portfolio. The 220/11//20 kV Vetiș transformer station is located in Satu Mare, with Transelectrica SA - ST Cluj as the beneficiary, and the modernization works took place over a period of 36 months.
As part of the modernization project, works were carried out that consisted in the replacement of the 220 kV and 110 kV primary equipment, constructions (foundations, metal supports), hydrotechnical installations (collection and drainage of rain and household water), land systematization and access road development. The project is a benchmark and corresponds to the development directions addressed by Transelectrica and provided for in the "General concept regarding the remote control strategy of re-engineered power stations".